LNG Receiving Terminal Expasion Project-Phase II


Rayong, Thailand

Owner:

PTT.

Project:

LNG Receiving Terminal Expansion Project – Phase II

Engineer:

Tokyo Gas Engineering Co.,Ltd.

Main Contractor:

IHI corporation

Foundation Contractor:

Thai Bauer Co.,Ltd and Others.

Scope of Works:

 

 

·         12 nos of Pilot Bored Piles & Anchor Piles Ø 1200 mm. x 20.0 m. deep.

·         616 nos of Working Bored Piles Ø 1200 mm. x 20.0 m. deep.v.

 

Construction Period:

Jun  – Oct  2014

Main Equipment:

1 no.of BG 24 V , 2 no.of BG 25 ,  1 no.of BG 28 &  3 no.of 50 ton crawler crane.